Sample 90‑day plan
An illustrative example of the ranked plan a systems audit ends with. The contractor is fictional and so is every detail below; it is not a real client’s plan.
- Status
- Illustrative example
- Scenario
- A fictional building contractor with about 30 staff
- Changes
- 7, in ranked order
The fictional contractor
A building contractor with about 30 staff, working on contracts under £5 million. Estimating, site and the office keep their records in SharePoint, personal OneDrive folders and spreadsheets.
In this example the audit found drawings issued from personal folders, an O&M and test certificate tracker that one coordinator updates, no rules on using AI tools and new starters learning the systems by asking around.
The ranked changes
Each change says why it matters, the effort, what it depends on, when in the 90 days it falls and who leads it. The ranking weighs consequence, effort and dependency.
- 01
Agree one naming and revision convention
Drawings and RAMS are saved as "final", "final v2" and "latest", so the current revision depends on who you ask. Every later change in this plan relies on one convention.
- Effort
- About 1 day, with the document controller and 2 project managers
- Depends on
- Nothing
- When
- Days 1 to 10
- Owner
- Document controller
- 02
Issue drawings from one SharePoint library
Site teams print from personal OneDrive folders. A superseded revision can reach site, and nothing shows which revision was issued or who approved it.
- Effort
- About 3 days to set up the library and move live jobs
- Depends on
- Change 1
- When
- Days 10 to 30
- Owner
- Document controller, with IT support
- 03
Set a one-page AI use policy
Staff paste tender documents into free AI tools. The policy says which tools are allowed, what must never be pasted in and who checks the output before it is used.
- Effort
- About 1 day
- Depends on
- Nothing
- When
- Days 1 to 20
- Owner
- Managing director
- 04
Replace the handover tracker spreadsheet
One coordinator keeps the O&M and test certificate tracker up to date. When they are away, nobody knows what is outstanding before practical completion.
- Effort
- About 5 days, including a trial on 2 live jobs
- Depends on
- Change 2, so the tracker can link to issued documents
- When
- Days 30 to 75
- Owner
- Commercial manager
- 05
Write a first-week guide for new starters
New site managers find out where things live by asking around, and pick up the habits changes 1 and 2 are meant to stop.
- Effort
- About 2 days
- Depends on
- Changes 1 and 2
- When
- Days 45 to 60
- Owner
- Operations director
- 06
Train site and office teams on the library and tracker
A new structure lasts only if people know which record to fill in and why. Two short sessions on the live system, each followed by a one-page task guide.
- Effort
- About 2 days, including the task guides
- Depends on
- Changes 2 and 4
- When
- Days 60 to 80
- Owner
- Operations director
- 07
Decide whether to connect the tracker to finance
Valuations are typed again from the tracker into the finance system. A connection could save that time, but only once the new tracker has run for a month.
- Effort
- Half a day to decide; any build is planned separately
- Depends on
- Change 4 running for a month
- When
- Days 80 to 90
- Owner
- Commercial manager